Header Weekend with Dave

Construction Area, Under Construction, Contract Site

Road Shoulder Works 
Westcliffs Avenue between Murray Avenue and Boomerang Avenue, Red Cliffs 
Start: 7am, Monday 29 June 2020 
Finish: 5pm, Friday 17 July 2020 
 
Road Reconstruction 
Curtis Road between O’Day Road and Walker Road, Wargan 
Start: 7am, Monday 1 June 2020 
Finish: 5pm, Friday 31 July 2020 
 
Sand Drift Removal 
Karawinna North Road between Millewa Road and Sturt Highway, Werrimull 
Start: 7am, Monday 15 June 2020 
Finish: 5pm, Friday 31 July 2020 
Merrinee North Road between Millewa Road and Sturt Highway, Merrinee 
Start: 7am, Monday 29 June 2020 
Finish: 5pm, Friday 31 July 2020 
 
Road Reconstruction 
Eighth Street between Walnut Avenue and the Railway Line, Mildura 
Start: 7am, Monday 30 March 2020 
Finish: 5pm, Friday 31 August 2020 
Millewa Avenue between Sixteenth Street and Dairtnunk Avenue, Irymple 
Start: 7am, Monday 1 June 2020 
Finish: 5pm, Friday 28 August 2020 
Cocklin Avenue between Kiewa Avenue and Cassia Street North, Red Cliffs 
Start: 7am, Monday 22 June 2020 
Finish: 5pm, Friday 4 September 2020 
 
Drainage Works 
Etiwanda Avenue and Gordon Avenue intersection, Mildura 
Start: 7am, Monday 13 July 2020 
Finish: 5pm, Friday 17 July 2020 
McCracken Street and Campbell Avenue intersection, Irymple 
Start: 7am, Wednesday 29 July 2020 
Finish: 5pm, Thursday 20 August 2020
 
Asphalt Works 
Seventh Street and Trafalgar Drive roundabout, Mildura 
Start: Friday 10 July 2020 
Finish: Saturday 11 July 2020
 
Utility Works
Commercial Street from Railway Avenue to Main Avenue North, Merbein
Start: 05/06/2020
End: 28/07/2020
Road Maintenance
Wentworth Road from Meridian Road to Hoyle Road, Yelta
Start: 25/05/2020
End: 31/07/2020
 
Road Construction Works
Calder Highway (A79) from Yetman Lane to Arnold Street, Ouyen
Start: 09/02/2020
End: 30/06/2020
 
Traffic Alert
Sturt Highway Mildura, George Chaffey Bridge
A NSW checkpoint is in place at the border to contain the spread of COVID-19. 
If you’re travelling from Victoria to NSW, you’ll need a COVID-19 NSW border declaration permit. 
Contact the Border Closure Hotline on 13 77 88 for more information, or visit service.nsw.gov.au. 
Calder Highway Yelta, Abbottsford Bridge 
Open for drivers heading from NSW into Victoria.
From tomorrow (Monday July 13) the bridge will be opened from Victoria into NSW but there will be a border checking station meaning residents will need to have their permit displayed.
If you’re travelling from Victoria to NSW, you’ll need a COVID-19 NSW border declaration permit. 
Contact the Border Closure Hotline on 13 77 88 for more information or visit service.nsw.gov.au. 
The border between Victoria and South Australia (SA) is closed. 
For most Victorians, this means entering South Australia will not be possible.
Victorians, including freight services, needing to travel into SA must obtain a Cross Border Travel Registration and essential traveller status.
Applications for cross border travel can be made via police.sa.vic.gov.au - it is recommended to apply at least three days prior to travelling.
 
Roads closed to the west of Mildura due to sand drift:
Keera Road from O’Day Road, Wargan to Sturt Highway, Merrinee
Keera Road from O’Day Road to Amos Lane, Wargan
O’Day Road from Sturt Highway, Merrinee to Keera Road, Wargan
Robertson Lane from Keera Road, Cullulleraine to Sturt Highway, Merrinee
Karawinna North Road from Sturt Highway to Tunkin Road, Merrinee
Baker Road near Bambill North Road, Werrimull
Yarrara North Road from Sturt Highway to Weatherhead Road, Meringur
Karween North Road from Sturt Highway to Karween South Road, Meringur